More
    HomeTrendingHeadlinesAllahabad High Court fines Noida builder ₹2.5 lakh after homebuyer fights for...

    Allahabad High Court fines Noida builder ₹2.5 lakh after homebuyer fights for 13 years over delayed possession of flat

    Published on

    spot_img

    The Allahabad High Court fined a Noida builder ₹2.5 lakh after a homebuyer was forced into litigation for nearly 13 years over delayed possession. The court also upheld 24% annual interest on the delayed possession, offering a key relief for homebuyers facing prolonged builder disputes.

    The Allahabad High Court has imposed a ₹2.5 lakh cost on a builder after a Noida homebuyer was forced into multiple rounds of litigation for nearly 13 years over delayed possession of a flat. The court also upheld 24% annual interest payable to the homebuyer for the delay, LiveLaw reported.

    The case involved M/s Aims Max Gardenia Developers Pvt. Ltd. and homebuyer Pratibha Gupta. The buyer had paid ₹35.90 lakh for a flat in the developer’s Golf City project in Sector 75, Noida. Under an agreement signed in April 2011, possession was promised by June 2013. However, the builder failed to hand over the flat as promised.

    Builder failed to comply with RERA order

    The homebuyer approached the Real Estate Regulatory Authority in Gautam Budh Nagar. In July 2018, the authority directed the builder to hand over possession and pay interest at 24% per annum from 30 June 2013.

    The builder did not comply with the order. Following execution proceedings, a recovery certificate of ₹41.21 lakh was issued in March 2019.

    The builder challenged the recovery proceedings before the Uttar Pradesh Real Estate Appellate Tribunal and subsequently approached the Allahabad High Court. The tribunal dismissed the builder’s appeal for want of prosecution. The appeal had already been dismissed twice on the same ground before being restored.

    The homebuyer later approached the High Court seeking enforcement of the recovery certificate and also initiated contempt proceedings when the order remained unenforced. After the builder’s bank accounts were attached, it deposited ₹67.78 lakh in December 2022 and filed the present appeal.

    Court upholds 24% interest on delayed possession

    The Allahabad High Court rejected the builder’s reliance on disruptions caused by the Covid-19 pandemic, holding that the developer had failed to demonstrate reasonable diligence in fulfilling its obligations.

    Latest articles

    400 Noida Families Don’t Have Water. Children Scrape Leaked Pipe For Drops

    Residents of Valmiki Basti in Sector 78 have been facing a water shortage for...

    Murder In Noida, Arrest In Bihar: How 5 Litres Of Liquor Led Cops To Killer

    The victim, identified as Mahak Ahmed, was found murdered on the night of August...

    “No Child Could’ve Swum Out”: Boy, 6, Drowns In 15-Foot Pit At Noida Housing Complex

    The boy was playing cricket with his friends when he fell into the pit,...

    Chinese national among 3 arrested in Noida over hawala, shell company network

    The Uttar Pradesh STF arrested a Chinese national and two associates in Noida over...

    More like this

    400 Noida Families Don’t Have Water. Children Scrape Leaked Pipe For Drops

    Residents of Valmiki Basti in Sector 78 have been facing a water shortage for...

    Murder In Noida, Arrest In Bihar: How 5 Litres Of Liquor Led Cops To Killer

    The victim, identified as Mahak Ahmed, was found murdered on the night of August...

    “No Child Could’ve Swum Out”: Boy, 6, Drowns In 15-Foot Pit At Noida Housing Complex

    The boy was playing cricket with his friends when he fell into the pit,...